QMines draws in $5.5M for Mt Chalmers development

QMines secures $5.5m in placement commitments, exceeding its $5m targetQIC-managed Queensland Critical Minerals Fund among participating investorsProceeds to support Mt Chalmers DFS, exploration and strategic land…

QMines draws in $5.5M for Mt Chalmers development
  • QMines secures $5.5m in placement commitments, exceeding its $5m target
  • QIC-managed Queensland Critical Minerals Fund among participating investors
  • Proceeds to support Mt Chalmers DFS, exploration and strategic land acquisitions

Special Report: QMines has secured firm commitments for a strongly subscribed $5.5 million placement, giving the Queensland copper-gold developer additional financial firepower to accelerate its push towards production at Mt Chalmers.

The placement attracted support from existing shareholders and new institutional investors, including the Queensland Critical Minerals Fund, managed by Queensland Investment Corporation (QIC), in another show of confidence in the development ambitions of QMines (ASX:QML).

The company received commitments above its original $5 million target, with 105.56 million new shares to be issued at 5.2c apiece, representing a 13.3% discount to the last traded price of 6c.

The raising will strengthen QMines’ ability to complete its definitive feasibility study, continue exploration and secure strategic freehold land required to support the proposed Mt Chalmers development.

It would also give QMines an estimated funding position of around $17.5 million, comprising $10.7 million in existing cash, $5.5 million in placement commitments before costs, and up to $1.4 million in deferred proceeds from the sale of its QDrilling subsidiary.

QMines executive chairman Andrew Sparke said the placement demonstrated strong investor support for the company’s strategy.

“We are delighted with the strong support shown for this Placement, with a number of investors introduced to the register,” Sparke said.

“The support for the Placement confirms backing for our strategy to bring Mt Chalmers into production. The additional capital strengthens our ability to secure strategic land, progress the DFS and maintain momentum across our extensive drilling programs.”

Queensland backing continues

The latest participation by the QIC-managed fund follows a $15 million strategic investment package announced in April, further strengthening the relationship between QMines and its state-backed investor.

That earlier agreement comprised a $5 million equity investment and a $10 million royalty investment in exchange for a 2% net smelter return royalty.

The arrangement provided funding to progress the Mt Chalmers DFS and associated development activities, while demonstrating QIC’s interest in supporting the proposed Central Queensland copper-gold production hub.

That support has accompanied an increasingly active period for QMines, which has advanced feasibility studies, environmental approvals and an extensive drilling campaign across Mt Chalmers and neighbouring targets.

Mt Chalmers, about 17km northeast of Rockhampton, hosts a resource of 11.3Mt at 0.75% copper and 0.42g/t gold, including an ore reserve of 9.6Mt at 0.65% copper and 0.48g/t gold.

The historic mine produced 1.2Mt of ore between 1898 and 1982, with QMines now pursuing a staged restart supported by modern resource modelling, metallurgical testwork and engineering studies.

An earlier pre-feasibility study outlined a 10.4-year mine life, an estimated $373 million pre-tax NPV and a 54% IRR.

The updated study is assessing a proposed 1Mtpa operation, alongside a potential 2Mtpa expansion case incorporating feed from the nearby Develin Creek copper-zinc project.

These remain development scenarios under assessment, with the DFS intended to refine the project’s capital requirements, operating costs and mining strategy.

Exploration offers another growth lever

QMines’ additional financial capacity comes as drilling continues to deliver encouraging copper-gold results beneath the historic Mt Chalmers open pit.

The company recently reported an intersection of 30.47m at 1.24% copper and 0.87g/t gold, including 9.47m at 2.36% copper and 2.14g/t gold, from diamond drilling conducted beneath the flooded pit.

Those downhole intersections, for which true widths remain unknown, will contribute to an updated resource assessment and potentially inform the developing mine plan.

The broader multi-rig campaign is also targeting Botos and Woods Shaft, with QMines seeking to expand its resource inventory and assess opportunities to incorporate additional deposits into a longer-term regional mining operation.

Land access is another priority. In September, QMines agreed to acquire two freehold properties covering about 25.5 hectares over and adjacent to the Botos mineralised area, improving its ability to advance drilling and assess future development opportunities.

Sparke said the company’s immediate attention remained firmly on bringing Mt Chalmers towards production while pursuing additional growth.

“Our immediate focus remains the staged development of Mt Chalmers, initially targeting a 1Mtpa operation, while testing opportunities to expand the resource base and future mine plan,” he said.

This article was developed in collaboration with QMines, a Stockhead advertiser at the time of publishing.

This article does not constitute financial product advice. You should consider obtaining independent advice before making any financial decisions.

The post QMines draws in $5.5M for Mt Chalmers development appeared first on Stockhead.

Source: Stockhead — Australian Stock Market ↗

Figures reflect the source report and its stated period. This article is for information and is not investment advice.